Bayfancy Residence completes its foundation piles: more than 350, driven 12 to 15 metres deep
Construction of Bayfancy Residence began on 1 December 2024. Within four weeks, more than 350 foundation piles had been driven 12 to 15 metres into the ground, three days ahead of plan, and steel sheet piling for the basement followed.

Work on Bayfancy Residence began on 1 December 2024, and its first task was the one buyers never see: the foundation.
The piles
Bayfancy chose a pile foundation after studying the ground. It drove more than 350 piles, each 12 to 15 metres deep, so that the weight of the building rests on the firmer layers below rather than on surface soil.
That matters on reclaimed land. Deep piles spread the load and limit the slow settling and tilting that can show up years after a building is finished. The method is standard for high-rise buildings in coastal cities from Singapore to Hong Kong.
During the month HDC, which manages Hulhumalé's land, briefed the developer on health and safety for the site.
Ahead of plan
The piling finished on 27 December 2024, three days before the planned date of 30 December. Two days later, on 29 December, steel sheet piling went in around the site and excavation of the basement began.
What came next
Over the following weeks the team cut the piles down to level, poured concrete and waterproofed the base of the basement. That set up the basement slab, the last step below ground.
Written for Binga's Bayfancy record on 18 October 2026 from the developer's announcements and press coverage at the time. Dated to the event it reports.
Ask the concierge about Bayfancy Residence
Sources and method
- mihaaru.com/business/140799 (Mihaaru, 12 December 2024: pile foundation, more than 350 piles at 12–15 m; HDC safety briefing)
- edition.mv/business/42557 (The Edition, 15 July 2025: piling started 1 December 2024, finished 27 December against a plan of 30 December; sheet piling and excavation from 29 December)
- bayfancy.com/news (Bayfancy news, "Sheet Piles In Progress", 29 December 2024; "Build-Insights", 25 December 2025)
Prices are asking prices as listed through Binga unless marked achieved, and are dated. Developer descriptions are reported as the developer's own. Facts the desk could not verify are left out. This piece was last updated 18 October 2026. Spotted an error? Write to hello@binga.mv; corrections are noted at the foot of the piece.
- Area Hulhumalé Phase 2
- For buyers
- Organisation Bayfancy PTE LTD
- Development Bayfancy Residence
- Topic construction
Binga Properties is a real-estate concierge; it may represent homes and developments mentioned here.