Bayfancy Residence, the full story: from the first pile to a June 2027 handover

Everything about Bayfancy Residence in one place: the Singapore developer behind it, the 18-storey building on Lot 20092 in Hulhumalé Phase 2, every milestone since piling began in December 2024, the handover date as it has moved, prices then and now, and what is left before keys in June 2027.

Bayfancy Residence as designed: the 18-storey tower on Lot 20092, Hulhumalé Phase 2. Render: Bayfancy
Bayfancy Residence as designed: the 18-storey tower on Lot 20092, Hulhumalé Phase 2. Render: Bayfancy

Bayfancy has reported the construction of Bayfancy Residence almost week by week since the first pile went in, from slab-by-slab notices to monthly engineering reports. Here is the full record. Each dated milestone below links to our report on it.

At a glance

DeveloperBayfancy PTE LTD, a Singapore developer re-registered in the Maldives
AddressLot 20092, Hulhumalé Phase 2 (the neighbouring plot, 20094, is Blue Lagoon Luxury Residences)
Building18 storeys over a basement, on more than 350 piles driven 12 to 15 metres deep
Homes1+1, two-bedroom, 2+1 and 3+1 apartments, and sky villas of 6,100–6,500 sq ft
For residentsA full amenity floor on level 17 (infinity pool, gym, yoga studio, play area, co-working, multipurpose hall), a double-height lobby and a planned butler service; no shops in the building
Construction started1 December 2024
Progress72 per cent (October 2026 report)
Expected handover30 June 2027

The timeline

Bayfancy's own report dates its completed milestones as: foundation works, March 2025; superstructure, October 2025; masonry, February 2026; plastering, August 2026.

The handover date, as it has moved

When it was saidHandover
July 2025, sales director's interviewSeptember to December 2026
December 2025, with the new investor31 December 2026
September–October 2026, monthly report30 June 2027

The current date is six months later than the one given last December. The frame was fast: ten and a half months from first pile to topping out. The interior has taken longer than the early schedule allowed.

One detail for buyers to raise: the header of Bayfancy's September report still says handover "30th of June 2026", while its own schedule in the same report runs to 30 June 2027. We read the schedule as correct. Ask the developer to confirm the date in writing.

Prices, then and now

LayoutFrom, May 2025From, September 2026
1+1MVR 3.5 million (about 735 sq ft)MVR 3.75 million
Two-bedroomMVR 4.1 million (859–906 sq ft)MVR 5.06 million
2+1MVR 5.2 million (about 1,133 sq ft)MVR 6.42 million
3+1MVR 6.2 million (1,551–1,925 sq ft)MVR 7.23 million
Sky villaMVR 26 millionnot stated

"From" prices may reflect which homes are still unsold as well as changes to the price list. Read together, they show starting prices about 7 per cent higher for the 1+1 and between 17 and 23 per cent higher for the larger layouts, sixteen months on. Bank of Maldives was named as mortgage partner at the 2025 launch.

Where the site stands (October 2026)

Bayfancy's October report lists thirteen works under way, most due by the end of the month:

  • Top floors: aluminium doors and windows starting on levels 16–18, and the external scaffolding starting to come down from levels 17–18.
  • Outside the building: facade drainage pipes on levels 15–18, half done.
  • Throughout: incoming electrical lines and smoke-detector wiring on levels 8–16 at 60 per cent, garbage-chute sealing from the ground floor up, and fire doors on the service shafts.
  • Upper middle floors: ceilings closing on level 17 and levels 9–10, and putty and tiling on levels 10–11 (30 and 40 per cent).
  • Lower floors: floor levelling on levels 4–6, and water and electrical pipes on levels 5–7.
  • Air-conditioning: levels 7–8, half done.

What is left: the road to handover

StageExpected
Second-fix services (MEP)30 December 2026
Waterproofing and floor preparation10 January 2027
Lifts installed and commissioned15 January 2027
Doors, windows and glazing20 January 2027
Fire and life-safety systems10 March 2027
Common areas and the level-17 amenities10 March 2027
Facade, external works and utility connections30 March 2027
Ceilings, tiling and flooring30 April 2027
Final-fix services and fixtures10 May 2027
Painting and architectural finishes20 May 2027
Apartment fit-out and joinery; systems testing30 May – 1 June 2027
Inspection, snagging and repairs10 June 2027
Final inspections and approvals20 June 2027
Completion and handover30 June 2027

The schedule leaves about ten days between each of the last three stages. That leaves little room if inspections find work to redo. The windows and lifts due in January are the next dates to watch: if they hold, the rest of the schedule is credible.

If you are buying now

  1. Get the handover date in writing, and what the agreement provides if it moves again.
  2. Check what changed with the new shareholder in October 2025: who signs your agreement, and whether earlier buyers' contracts carry over unchanged.
  3. Fix the specification. Visit the materials showroom and ask for the brands and models you see to be named in the contract, or an equal standard.
  4. Ask for the service charge for the level-17 amenities, the butler service and the lifts before you commit.
  5. Compare the price per square foot with finished buildings nearby. A home you can move into today has no completion risk.

We will update this page with each monthly report. The concierge can walk you through Bayfancy alongside other new buildings in Hulhumalé Phase 2.

Ask the concierge about Bayfancy Residence

Sources and method

Prices are asking prices as listed through Binga unless marked achieved, and are dated. Developer descriptions are reported as the developer's own. Facts the desk could not verify are left out. Spotted an error? Write to hello@binga.mv; corrections are noted at the foot of the piece.

Binga Properties is a real-estate concierge; it may represent homes and developments mentioned here.